CSB Safety Bulletin: Management of Change
An eight-page Chemical Safety Board bulletin from August 2001 on two 1998 incidents, opening with a power loss at a delayed coking unit and the twelve hours it took to restore steam.

Safety Bulletin No. 2001-04-SB, an eight-page document from the U.S. Chemical Safety and Hazard Investigation Board dated August 2001, discusses two incidents that occurred in the United States in 1998. The first account begins with a power loss that interrupted process operations and stopped steam production. At a delayed coking unit, the on-line drum had been filling for about an hour and was roughly 7 percent full. The other drum was full and being cooled.
Power came back after two hours. Another ten hours passed before steam was reestablished, and during those hours the tarry oil in the piping between the furnace and the partly filled drum cooled.
The Board's subject is management of change in the chemical industry. It says the practice should cover operational deviations and variances as well as preplanned changes to technology, processes and equipment, so an unplanned power loss falls inside it.
Provenance
- Original source
- https://www.csb.gov/assets/1/20/moc082801.pdf
- Collected
- This copy
- 159 KB · 8 pages · archived here
- Rights
- Rights belong to someone else. The copy here supports the commentary on this page, and comes down on request.
- SHA-256
520d290a2a1d6a8205ab61a751eb34f7f030a3d77f2f6fc4ca3d2e76184a2626
Accession № 0131. If you hold rights in this and would rather the copy did not exist, say so and it comes down.